48 Leicester Square, London, W1
Linseed Assets

PCSA Duraton: 23 weeks. Works Duration: 38 weeks.

£3.95m

City of Westminster
Overview
Design and build of a unique and technically challenging four sided façade retention within the heart of Westminster. Our 48 Leicester Sq project for Linseed Assets involved the complete internal demolition of the existing 1920s steel frame building whilst retaining all four external facades.
Relevant Experience
Due to extensive modifications since its original construction internal jacking and load testing needed to be carried out to
facilitate the demolition.
To provide the most efficient programme, the initial scaffold was cantilevered out from the top floors. This enabled the roof demolition to commence whilst the façade retention
system was installed.
Following the installation of 250T of steel for the façade retention system. The demolition commenced top down with midi sized demolition plant. This process enabled maximum recycling and reuse of the internal steel frame and concrete floors.
Located in one of the busiest parts of the West End, extensive planning, on going community engagement and having a flexible approach to the works were all key factors in
its success. The works were completed with very little disruption to the local area.
With the technical challenges and sensitive location, this project demonstrates John F Hunts commitment to quality and project delivery which was commended by being nominated as a Construction News Awards finalist.