Case Studies
77 Welbeck Street, London, W1G
77 Welbeck Street, LondonClient : Marylebone Lane LPProgramme : 91 weeksValue : £16mProject OverviewDeconstruction of an architecturally prominent, brutalist style 10-storey pre-cast concrete car park behind oxford street, close to the underground station....
Eastbourne Terrace, London, W2 – Phase 1, Demolition
Client : YardNine Programme : 52 weeks Value : £7m Download Case Study Project Background 50 Eastbourne Terrace is a significant site of 2,500m2 immediately adjacent to Paddington Station and the new entrance to the Crossrail Elizabeth Line. The completed...
Eastbourne Terrace, London, W2 – Phase 2, Basement & Core
Client : YardNine Programme : 80 weeks Value : £9m Download Case Study Scope of work Phase 1 & 2 Floor by floor demolition of three adjacent buildings requiring extensive propping to party walls and highways and pavements requiring AIPs. Long reach...
150 Holborn, London, EC1
Client : DAR Group Programme : 29 weeks Value : £2.4 m Download Case Study OVERVIEW A seven storey, 1980’s reinforced concrete building, constructed within London’s central business district on the corner of Chancery Lane...
132—142 Hampstead Road, London, NW1
Client : Costain Skanska JV on behalf of HS2 Programme : 46 weeks Value : Confidential Download Case Study OVERVIEW Located on Hampstead Road, buildings132-140 formed the original BHS warehouse which was subsequently used by the UCL School of Architecture and...
Queens Square, Croydon, London, CR0
Client : R&F Properties Programme : 44 weeks Value : £10.5m Download Case Study OVERVIEW We demolished six structures and broke out basement slabs whilst retaining the basement walls on a site covering 5.4 acres in busy Croydon...
Cityside House, London, E1
Client : Great Portland Estates Ltd Programme : 40 weeks Value : £2.8m Download Case Study OVERVIEW A project on the corner of Adler Street and Whitechapel High Road, a few yards from Aldgate East Station, with John F Hunt as Principal...
Kensington Odeon Cinema, London, W8
Client : Minerva / Delancey Programme : 37 weeks Value : £3m Download Case Study LOCATION & OVERVIEW Set in the heart of the Royal Borough of Kensington & Chelsea, the structure to be demolished was the iconic Kensington Odeon Cinema, located on...
New Bracken House – London, EC4M
Client : McLaren Construction Ltd Programme : 35 weeks Value : £3.3m Download Case Study LOCATION & OVERVIEW A 1958 built late example of modern classicism. Situated on a cleared bomb site, southeast of St Paul's Cathedral, this Grade II listed building...
Keybridge House, Vauxhall, London, SW8
Client : Mount Anvil Programme : 18 months Value : £12m Download Case Study LOCATION & OVERVIEW Keybridge house was previously owned by BT and is situated on a 1.35 hectare site on South Lambeth Rd, within the 9 Elms regeneration area. The site is approx....
Barking Riverside Extension
Client : TFLProgramme : 4 MonthsValue : £2.2M Download Case Study To watch our work please Click hereLOCATION & OVERVIEW The Barking Riverside Extension project is designed to enable transport links to the future housing developments in the area. The site...
The Fruit and Wool Exchange
Client : Exemplar Properties Programme : 74 weeks Value : £9 M Download Case Study Existing Structure & Location: The Fruit & Wool Exchange and adjoining multi storey car park was situated along Brushfield Street which is immediately opposite...
145 City Road, London EC1
Client : Rocket InvestmentsProgramme : 76 weeksValue : £17 M Download Case Study The old 1980’s built Crown House office building, on the busy City Road close to Moorfields Eye Hospital. Scope of Work Demolition: Removal of Asbestos Containing...
Centre Point, London, WC1A
Client : Almacantar Programme : 75 weeks Value : £11.75 M Download Case Study Overview The redevelopment of Centre Point is one of the most iconic London landmark projects to take place during recent years. The execution of major...
Bradwell Nuclear Power Station
Client : Vinci Construction UK Programme : 36 months Value : £9.4 M Download Case Study Overview: Bradwell, located in the South East of England, covers an area of 20 hectares. The nuclear power station operated from 1962 until 2002...
10 Fenchurch Avenue, London, EC3M
Client : Saxon Land Programme : 72 weeks Value : £11.2 M Download Case Study Overview The Fenchurch Avenue project is located close to Fenchurch Street Station within a busy area of the City of London. The demolition of No.10, 12...
80 Fenchurch Street, London, EC3M
Client : MarickProgramme : 36 weeksValue : £2.3m Download Case Study Overview Located along the densely pedestrianised area of Fenchurch Street adjacent to both Fenchurch Street Station and the busy area of Aldgate. The project comprised of the demolition of...
Crossrail – Liverpool Street
Client : Crossrail Programme : 18 Months Value : £6.3m Download Case Study Overview The Liverpool Street Crossrail project was split into three separate site locations, all were within close proximity of Liverpool Street or Moorgate Station. Each site had its...
48 Leicester Square, London, W1
Client : Linseed Value : £3.95 M PCSA Duraton: 23 weeks Works Duration: 38 weeks Download Case Study Overview Existing Structure & Location: For many years 48 Leicester Square has been an iconic island site landmark which dominates the western side of the...
5 Broadgate, London, EC2
Client : British Land Programme : 70 weeks Value : £6.5 M Download Case Study Overview This high profile project direct for British Land represented the first buildings to be demolished within the iconic 1980’s built Broadgate...
5 & 6 St James’s Square, London, SW1
Client : Exemplar Properties (ph1 works) Programme : 70 weeks Value : £4.8m Download Case Study Overview The former Lybian Embassy, No. 6 St James Square, was a 6 storey reinforced concrete brick clad Structure, which required...
Wembley Conference Centre, Elvin House & Exhibition Halls
Client : Quintain Estates Programme : 28 months Value : £4.5m Download Case Study Overview Existing Structure & Location: Demolition of the massive Wembley Conference Centre, which included two Exhibition Halls, linked footbridges, office blocks and...
Queens Court, Glasgow
Client : Glasgow Housing Association Trust Value : £1.3 M Overview A specialist team of operatives and explosive experts undertook the major 8 month preparation of the 22 storey building which included asbestos removal, soft strip and de-glazing of the...
Mitchellhill Residential Tower Blocks, Glasgow
Client : Glasgow Housing Association Ltd Programme : 24 weeks Value : £1.4m Download Case Study Overview The Explosive demolition of five 19 storey structures in Castlemilk, Glasgow. These 1965 built blocks were constructed of Wimpey No-Fines concrete and...
Convoys Wharf, London, SE8
Client : Hutchinson Property Group Ltd Programme : 12 weeks Value : £123k Download Case Study OVERVIEW Demolition of two warehouses down to ground level at Convoys Wharf, in Deptford, a 16.6 hectare derelict brownfield site. With almost 500 metres of river...
Royal Mail, Nine Elms Lane
Client : Royal Mail Group & M3 Consulting Value : £380,000 Download Case Study Overview Existing Structure & Location: The site was owned by the Royal Mail Group and used as one of the main sorting and distribution offices...
Get in Touch
John F Hunt Group - London Road, Grays, Essex, RM20 4DB
Tel: +44 (0)1375 366 700
Email: John F Hunt Info
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.