Environment
To minimise noise and disturbance whilst demolishing the rear RC structure no percussive hammers were used whatsoever. The machines were fitted with high performance NPK concrete cracking attachments specially purchased for the job and flexibility of working was placed under the most intense levels of scrutiny.
Dust control was also paramount to the projects success. Water was pumped to each working level and the most exacting standard of inspection was paid to the integrity of the Monarflex sheeting enclosing the work.
Delivery of Services
The main demolition contract was completed within the 26-week programme and £960k budget. Subsequently under a new order and extended programme we were awarded additional enabling works in relation to the party walls to facilitate readiness for the main contractor.. |